On June 13, 2002 Oscar Owens and his crew
poured the driveway and walkways. |
|
|
|
|
|
|
By August 12, 2002
the Hardi-board siding is installed, the lot is finished graded and the
framing for her porch columns is in place. The Columns and Stem wall
will get stucco this week. |
|
|
|